Litigation Support

Appointed as consultant by a contractor in arbitration against the employer of an international school project in respect of delay loss & expense claims.
Appointed as consultant by the contractor in arbitration with his sub-contractor on disputed final account for a hotel resort project in Malaysia.
Appointed as consultant to a contractor defending a claim from a competitor in court in relation to a breach of secrecy agreement and copyright laws on the manufacture and supply of performance louvers in Singapore.
Appointed as consultant to a contractor defending a claim in the High Court for contended progress claims valuation for a railway works project in Malaysia.
Appointed as consultant to a contractor in mediation with his sub-contractors on EOT claims for a major commercial development in Petaling Jaya, Malaysia.
Appointed as consultant to a main contractor defending a claim in litigation for damages arising from delay and wrongful termination of a sub-contract for works relating to the construction of an integrated oil & gas complex in Malaysia.
Appointed as consultant to a main contractor defending a claim by a sub-contractor in litigation for loss and expense claims arising from a piping and ducting works contract for a 1000MW Coal Fired Power Plant in Malaysia.
Appointed as consultant to a main contractor raising a claim against the Employer in arbitration in relation to delays, loss and expense on a highway and bridges Contract in Hanoi, Vietnam.
Appointed as consultant to a main contractor raising a claim against the Employer in arbitration in relation to delays, loss and expense on a solar panel manufacturing plant in Malaysia.
Appointed as consultant to a main contractor raising a claim against the employer in arbitration in relation to delays, loss and expense on two highway and bridges contracts in Ho Chi Minh City, Vietnam.
Appointed as consultant to a sub-contractor raising a claim against a contractor in court in relation to non-payment for works and related losses on a MRT Station project in Singapore.
Appointed as consultant to a sub-contractor raising a claim against a main contractor in arbitration in relation to increase in complexity of works on an airport project in Singapore.
Appointed as consultant to an employer defending a claim from a main contractor in arbitration in relation to delays, loss and expense on a high-rise commercial building development in Singapore.
Appointed as management representative for a contractor defending a claim in arbitration in relation to variations, delays and loss and expense on a customs and immigration complex project in Singapore.
Appointed as management representative for a contractor defending numerous claims from sub-contractors in court in relation to payment disputes for numerous construction projects in Singapore.
Appointed as management representative for a sub-contractor raising a claim against a main contractor in arbitration in relation to variations, and loss and expense resulting from delays on an airport project in Singapore.